Stowe Elementary received $.5 Million with another $.5 Million budgeted next year.

  • 2010--Installed new trash enclosure and cedar fence, a new interior and exterior ramped accessible
    entry and new interior and exterior ADA complaint signage. Relocated kitchen to expand the existing serving area, renovated existing lunchroom 010 and created a new music room. $561,651
  • 2015--Summer Priority Project will include providing window AC units for all classrooms. $300,717
  • 2015--Summer Priority Project will include providing a new double play lot, including one that will serve ages 3-5 and one that will serve ages 5-12. $226,568